Software Cost Estimation Ian Sommerville 2000 Software Engineering, 6th edition. Chapter 23 Slide 1
Software cost estimation Predicting the resources required for a software development process Ian Sommerville 2000 Software Engineering, 6th edition. Chapter 23 Slide 2
Fundamental estimation questions How much effort is required to complete an activity? How much calendar time is needed to complete an activity? What is the total cost of an activity? Project estimation and scheduling and interleaved management activities Ian Sommerville 2000 Software Engineering, 6th edition. Chapter 23 Slide 3
Software cost components Hardware and software costs Travel and training costs Effort costs (the dominant factor in most projects) salaries of engineers involved in the project Social and insurance costs Effort costs must take overheads into account costs of building, heating, lighting costs of networking and communications costs of shared facilities (e.g library, staff restaurant, etc.) Ian Sommerville 2000 Software Engineering, 6th edition. Chapter 23 Slide 4
Costing and pricing Estimates are made to discover the cost, to the developer, of producing a software system There is not a simple relationship between the development cost and the price charged to the customer Broader organisational, economic, political and business considerations influence the price charged Ian Sommerville 2000 Software Engineering, 6th edition. Chapter 23 Slide 5
Software pricing factors Ian Sommerville 2000 Software Engineering, 6th edition. Chapter 23 Slide 6
Programmer productivity A measure of the rate at which individual engineers involved in software development produce software and associated documentation Not quality-oriented although quality assurance is a factor in productivity assessment Essentially, we want to measure useful functionality produced per time unit Ian Sommerville 2000 Software Engineering, 6th edition. Chapter 23 Slide 7
Productivity measures Size related measures based on some output from the software process. This may be lines of delivered source code, object code instructions, etc. Function-related measures based on an estimate of the functionality of the delivered software. Function-points are the best known of this type of measure Ian Sommerville 2000 Software Engineering, 6th edition. Chapter 23 Slide 8
Measurement problems Estimating the size of the measure Estimating the total number of programmer months which have elapsed Estimating contractor productivity (e.g. documentation team) and incorporating this estimate in overall estimate Ian Sommerville 2000 Software Engineering, 6th edition. Chapter 23 Slide 9
Lines of code What's a line of code? The measure was first proposed when programs were typed on cards with one line per card How does this correspond to statements as in Java which can span several lines or where there can be several statements on one line What programs should be counted as part of the system? Assumes linear relationship between system size and volume of documentation Ian Sommerville 2000 Software Engineering, 6th edition. Chapter 23 Slide 10
Productivity comparisons The lower level the language, the more productive the programmer The same functionality takes more code to implement in a lower-level language than in a high-level language Ian Sommerville 2000 Software Engineering, 6th edition. Chapter 23 Slide 11
High and low level languages Ian Sommerville 2000 Software Engineering, 6th edition. Chapter 23 Slide 12
Function points Based on a combination of program characteristics external inputs and outputs user interactions external interfaces files used by the system A weight is associated with each of these The function point count is computed by multiplying each raw count by the weight and summing all values Ian Sommerville 2000 Software Engineering, 6th edition. Chapter 23 Slide 13
Object points Object points are an alternative function-related measure to function points Object points are NOT the same as object classes The number of object points in a program is a weighted estimate of The number of separate screens that are displayed The number of reports that are produced by the system The number of modules that must be developed Ian Sommerville 2000 Software Engineering, 6th edition. Chapter 23 Slide 14
Productivity estimates Real-time embedded systems, 40-160 LOC/P-month Systems programs , 150-400 LOC/P-month Commercial applications, 200-800 LOC/P-month In object points, productivity has been measured between 4 and 50 object points/month depending on tool support and developer capability Ian Sommerville 2000 Software Engineering, 6th edition. Chapter 23 Slide 15
Factors affecting productivity Ian Sommerville 2000 Software Engineering, 6th edition. Chapter 23 Slide 16
Quality and productivity All metrics based on volume/unit time are flawed because they do not take quality into account Productivity may generally be increased at the cost of quality It is not clear how productivity/quality metrics are related If change is constant then an approach based on counting lines of code is not meaningful Ian Sommerville 2000 Software Engineering, 6th edition. Chapter 23 Slide 17
Estimation techniques There is no simple way to make an accurate estimate of the effort required to develop a software system Initial estimates are based on inadequate information in a user requirements definition The software may run on unfamiliar computers or use new technology The people in the project may be unknown Project cost estimates may be self-fulfilling The estimate defines the budget and the product is adjusted to meet the budget Ian Sommerville 2000 Software Engineering, 6th edition. Chapter 23 Slide 18
Estimation techniques Algorithmic cost modelling Expert judgement Estimation by analogy Parkinson's Law Pricing to win Ian Sommerville 2000 Software Engineering, 6th edition. Chapter 23 Slide 19
Algorithmic code modelling A formulaic approach based on historical cost information and which is generally based on the size of the software Discussed later Ian Sommerville 2000 Software Engineering, 6th edition. Chapter 23 Slide 20
Expert judgement One or more experts in both software development and the application domain use their experience to predict software costs. Process iterates until some consensus is reached. Advantages: Relatively cheap estimation method. Can be accurate if experts have direct experience of similar systems Disadvantages: Very inaccurate if there are no experts! Ian Sommerville 2000 Software Engineering, 6th edition. Chapter 23 Slide 21
Estimation by analogy The cost of a project is computed by comparing the project to a similar project in the same application domain Advantages: Accurate if project data available Disadvantages: Impossible if no comparable project has been tackled. Needs systematically maintained cost database Ian Sommerville 2000 Software Engineering, 6th edition. Chapter 23 Slide 22
Parkinson's Law The project costs whatever resources are available Advantages: No overspend Disadvantages: System is usually unfinished PL states that work expands to fill the time available. The cost is determined by available resources rather than by objective statement. Example: Project should be delivered in 12 months and 5 people are available. Effort 60 p/m Ian Sommerville 2000 Software Engineering, 6th edition. Chapter 23 Slide 23
Pricing to win The project costs whatever the customer has to spend on it Advantages: You get the contract Disadvantages: The probability that the customer gets the system he or she wants is small. Costs do not accurately reflect the work required Ian Sommerville 2000 Software Engineering, 6th edition. Chapter 23 Slide 24
Top-down and bottom-up estimation Any of these approaches may be used top-down or bottom-up Top-down Start at the system level and assess the overall system functionality and how this is delivered through sub-systems Bottom-up Start at the component level and estimate the effort required for each component. Add these efforts to reach a final estimate Ian Sommerville 2000 Software Engineering, 6th edition. Chapter 23 Slide 25
Estimation methods Each method has strengths and weaknesses Estimation should be based on several methods If these do not return approximately the same result, there is insufficient information available Some action should be taken to find out more in order to make more accurate estimates Pricing to win is sometimes the only applicable method Ian Sommerville 2000 Software Engineering, 6th edition. Chapter 23 Slide 26
Experience-based estimates Estimating is primarily experience-based However, new methods and technologies may make estimating based on experience inaccurate Object oriented rather than function-oriented development Client-server systems rather than mainframe systems Off the shelf components Component-based software engineering CASE tools and program generators Ian Sommerville 2000 Software Engineering, 6th edition. Chapter 23 Slide 27
Pricing to win This approach may seem unethical and unbusinesslike However, when detailed information is lacking it may be the only appropriate strategy The project cost is agreed on the basis of an outline proposal and the development is constrained by that cost A detailed specification may be negotiated or an evolutionary approach used for system development Ian Sommerville 2000 Software Engineering, 6th edition. Chapter 23 Slide 28
Algorithmic cost modelling Cost is estimated as a mathematical function of product, project and process attributes whose values are estimated by project managers Effort A SizeB M A is an organisation-dependent constant, B reflects the disproportionate effort for large projects and M is a multiplier reflecting product, process and people attributes Most commonly used product attribute for cost estimation is code size Most models are basically similar but with different values for A, B and M Ian Sommerville 2000 Software Engineering, 6th edition. Chapter 23 Slide 29
Estimation accuracy The size of a software system can only be known accurately when it is finished Several factors influence the final size Use of COTS and components Programming language Distribution of system As the development process progresses then the size estimate becomes more accurate Ian Sommerville 2000 Software Engineering, 6th edition. Chapter 23 Slide 30
- NEXT LECTURE Wednesday, 9.00 am Ian Sommerville 2000 Exam structure How to pass Multiple choice exam Mock exam questions etc Software Engineering, 6th edition. Chapter 23 Slide 31