Project Plan The Development Plan  The project plan is one of

20 Slides132.00 KB

Project Plan The Development Plan The project plan is one of the first formal documents produced by the project team. It describes How the project will be developed How resources will be required How the resources will be used The timely provision of equipments and tools Provision of contingency plan in the event that project risks materialize Task designations

Software Project Development Plan Software development project plan Other standards includes the IEEE standard 1058 which is called software project management plan PMI’s project management plan

Project Scheduling Project Schedule Activities Resources especially people The project schedule answers two basic planning questions What and when How:

Scheduling What Activities and Milestones List of activities and their expected time of implementation Diagrams (e.g. PERT network diagrams) Table Charts (e.g. Gantt charts) Graphs All this present two important information Activities Time of implementation

Is it possible to get a full list of all the activities in the beginning of the project?

Scheduling The HOW discussion includes the following How risk will be handled How the project will be organized How reviews will be conducted How standard will applied What methodology will be used and How the product will be tested.

Scheduling The Activity List This is often developed with the work breakdown structure (WBS) table The WBS breaks down all project activities to a much lower level, called work tasks. A schedule list of activities contains the following information: Activity ID, Activity name, Description, start date, completion date, dependency, and responsibility. It is important that you two high priority activities don’t overlap.

Sample Activity List Activity Activity ID Name Description Start Date End Date Dependenci es Assignment Responsibilit y 5 Integratio n Software and hardware integration 5.1 Equipmen t Procureme nt of integration equipment Jan 10 Jan 31 5.3 Ali (Baba), N. 5.3 Integratio n plan Prepare integration plan Jan 1 Jan 28 Ellyn Mann

Scheduling Milestone and Baselines Milestone are used as points of payment, measurement of progress on the project and for determining baselines. IEEE definition of baseline includes “a formally agreed specification that then serves as the basis for further development” Functional baseline: This document is the basis for all design and implementation, and in particularly it is the basis for system testing and acceptance.

Gantt Chart Requirement analysis Top level design Detailed design Implementation Integration Testing Maintenance Jan. Feb Mar Apr May June July Aug Sep Oct Nov Dec.

Gantt Chart - Integration Set Integration site Integrate Phase I Integrate executive Integrate OS Integrate user interface Integrate phase II Integrate hardware Integrate communications Integrate full system Integrate main computer Maintenance Mar April June July August

Gantt Charts Do Enable important schedule information to be grasped quickly Do not Does not provide information on the amount of resources required to complete each activity.

PERT Chart PERT (Program Evaluation and Review Technique) Used to plan project activities And to monitor their performance PERT Can address two important issues The need to identify dependences The need to ensure that responsibilities for each activity has been assigned.

PERT Chart A1,2 D1,2 Ax,y Dx,y Aij Activity at node i and ending at node j Dij Duration of activity Aij

PERT Chart: Critical Path 6 A1,2 D1,2 12 3 5 11 8 10 3 6 12 5 4 Critical path PERT 2 Ax,y Dx,y 6

Scheduling HR The most important and most valuable project resource is the development team (people) The team size The development team size is influenced by # of activities Intensity or complexity of the activities Skill

Development team size 18 16 14 Project setup Requirement Design Implementation Integration Testing Project Wrap-up 12 10 8 6 4 2 0 Time

Scheduling Resources Resources Work place Equipments Vendors and subcontractors

Scheduling Monitoring and updating the schedule It is not a static document Period report Schedule Update Checklist 1. Activity list 2. Personal assignment 3. Risk list and risk analysis 4. Resources allocation 5. Third party status (subcontractors, vendors, suppliers) 6. Schedule chart (Gantt) 7. Precedence network (PERT) 8. Approved requirements and design changes

Customer Perspective The customer is in the center of a project scheduling The customer is the most important project entity One measure of project success is the degree of customer satisfaction To promote customer satisfaction: Honest communication Continuous communication Maintain technical quality Make it easy to use Understand that there are different types of customers

Back to top button