PMI Knowledge Areas Project Cost Management
20 Slides674.30 KB
PMI Knowledge Areas Project Cost Management
Project Cost Management Processes Process Group Planning Monitoring and Controlling Cost Management Process Major Output CP1: Planning Cost Mgmt Cost Management Plan CP2: Estimating Costs Activity Cost Estimates CP3: Determining the Budget Cost Performance Baseline MC1: Controlling Costs Work Perf. Measurements Budget Forecasts 2
Types of Costs and Benefits Tangible costs or benefits Intangible costs or benefits Direct costs Indirect costs Sunk cost Basic Principles of Cost Management Learning curve theory Reserves Contingency reserves Management reserves
CP1: Planning Cost Management The project team uses expert judgment, analytical techniques, and meetings to develop the cost management plan A cost management plan includes: Level of accuracy and units of measure Organizational procedure links Control thresholds Rules of performance measurement Reporting formats Process descriptions
CP2: Estimating Costs Project managers must take cost estimates seriously if they want to complete projects within budget constraints It’s important to know the types of cost estimates, how to prepare cost estimates, and typical problems associated with IT cost estimates Input 1) HR Plan 2) Project Schedule 3) Scope Baseline 4) Risk Register Tools/Techniques 1) EstimatingTechniques 2) Cost of Quality 3) Reserve Analysis 4) PM Estimate Software 5) Expert Judgment Output 1) Activity cost estimates 2) Estimate Bases 3) Update docs 5
My Health Intranet Sites What are the primary costs for the intranet site project? What is the best way to create estimates for the project?
Categories of Cost Estimates The number and type of cost estimates vary by application area.
Cost Estimation Techniques Basic tools and techniques for cost estimates: Top-down estimates Analogous Parametric modeling
Cost Estimation Techniques Basic tools and techniques for cost estimates: Bottom-up estimates PERT Ex. The pessimistic cost estimate for an activity is 11,000, the optimistic estimate is 3,000 and the most likely estimate is 4,000. What should you use for the expected estimate?
Using Estimation Techniques Top-Down Technique Externally: used by organizations completing IT projects for other companies Internally: can be used for similar projects Problem You are dealing with IT Less Accurate Estimates
Using Estimation Techniques Bottom-up Technique Based on the WBS Creates a detailed estimate of each work component More Accurate Can separate across phases Would be better for controlling costs (Monday’s lecture)
Which technique is being used? Based on the description below, what kind of estimate is being used? It will take 20 hours of a programmer’s time to write this program. The average rate to hire a programmer is 50 per hour. Therefore, the cost of writing this program, assuming that everything else needed to write the program, such as a computer, is in place, is 20 x 50 1,000.
Typical Problems with IT Cost Estimates Estimates are done too quickly People lack estimating experience Human beings are biased toward underestimation Management desires accuracy Contingency reserve is often used to reduce the risk from these problems
PM Network: Estimates are just that “We are headed down the path of providing more precise estimates in an environment that is not as precise and where costs fluctuate greatly.” Managing estimates through the lifecycle Agile Estimating Formulas for success
PM Network: Estimating Errors “treat estimates as a living process and not a one time event.” Approaches Matching Skill Sets Share Accountability
Review: Cost Estimate Technique (Parametric, Reserve Analysis, Bottom-up Estimate, Three-point estimate) 1) It was discovered that there are many unknowns about an activity and that it could cost a lot of more than estimated because it could take longer. So, some money is put aside to deal with the situation 2) There is a complicated activity for which there are many disagreements among the team about its cost estimate. So, an estimate was created by taking the average optimistic estimate, pessimistic estimate and realistic estimate. 3) The manager still had doubts about the estimate above so the complex activity was split up into smaller pieces. Estimate costs were placed on these pieces and then all were added up to reach the final figure/ 4) For another activity, the number of work hours needed were multiplied by the hourly rate of a programmer
CP3: Determining the Budget Cost budgeting involves allocating the project cost estimate to individual work items over time The WBS is a required input to the cost budgeting process since it defines the work items Reserve analysis must occur Contingency reserves Management reserves
Figure 7-4. Surveyor Pro Project Cost Baseline
Chapter Summary Project cost management is a traditionally weak area of IT projects, and project managers must work to improve their ability to deliver projects within approved budgets Main processes include Plan cost management Estimate costs Determine the budget Control costs
CAPM – Things to know Project budget is time-phased project cost (aggregating individual activity costs) Contingency Reserves Deal with uncertainties in schedule/cost Deal with overruns of the project objectives Analogous estimating takes less time but is also less accurate Memorize the formulas for EV, CV, CPI, PV, SV, SPI